Musi Rejuvenation: HMWSSB asks officials to fast-track STPs under AMRUT 2.0
Ashok Reddy instructed that STP works must be completed within the stipulated schedule, with a target to finish construction by the end of this year
By - Sistla Dakshina Murthy |
Hyderabad: With a clear focus on the rejuvenation of the Musi River and preventing untreated sewage from polluting its waters, HMWSSB managing director Ashok Reddy on Wednesday directed officials to expedite the construction of Sewage Treatment Plants (STPs) under the AMRUT 2.0 scheme.
Apart from that, he also reviewed major drinking water and sewerage infrastructure projects across the city.
Fast-tracking STPs for Musi Rejuvenation
As part of efforts to stop direct sewage discharge into the Musi River, the MD inspected the 34.5 MLD-capacity STP at Narsingi, being executed under Package I of AMRUT 2.0.
He reviewed the pace of civil works and interacted with officials and construction agency representatives to ensure adherence to timelines.
Ashok Reddy instructed that STP works must be completed within the stipulated schedule, with a target to finish construction by the end of this year, stressing that uninterrupted work, adequate manpower, machinery and material deployment are essential.
Preventing sewage inflow into Musi
During the inspection of areas along the Musi, the MD directed officials to identify sewage entry points from nearby colonies and ensure diversion of wastewater through pipelines into the newly built STPs.
He emphasised that construction activities should not cause any damage to the river and that strict environmental safeguards must be followed.
Sewerage network and inter-departmental coordination
Officials were asked to prepare detailed plans for sewerage trunk mains and sub-mains in catchment areas such as Kokapet, Narsingi, upstream zones and surrounding localities, so that sewage can be effectively channelled to STPs.
He stressed close coordination with the Greater Hyderabad Municipal Corporation (GHMC) and the Telangana Irrigation Department to ensure the timely diversion of sewage and completion of allied works.
Godavari Phase 2 & 3 water supply projects
Earlier in the day, the MD inspected works under Godavari Phases 2 and 3 at Khanapur, where he reviewed the construction of the Water Treatment Plant (WTP).
Officials briefed him on construction progress and completion timelines, with directions issued to maintain quality and speed.
Neopolis integrated water supply
Ashok Reddy later reviewed the Neopolis integrated water supply project, holding discussions with senior officials of the Hyderabad Metropolitan Development Authority (HMDA) on land allocation for critical infrastructure such as balancing reservoirs, pumping stations, and WTPs.
He asked HMDA to submit detailed drawings and level data of drinking water and sewerage pipelines developed in Neopolis for seamless integration with HMWSSB systems.
HMWSSB is constructing two reservoirs of 2.5 million litres capacity each in Neopolis. Given the high land value in the area, the MD suggested examining the technical feasibility of a multi-level (two-floor) reservoir design to optimise land use and meet future demand.
STPs to protect twin reservoirs
To prevent sewage from entering the twin reservoirs, HMWSSB is constructing four STPs. As part of this initiative, the MD inspected the 4 MLD STP at Bulkapur Nala, Janwada, reviewing the progress of the Primary Treatment Unit (PTU).
He sought details of the catchment areas feeding into the STP and instructed officials to draw up a comprehensive trunk main plan, in coordination with HMDA, Irrigation and HYDRAA authorities, to divert sewage from surrounding villages.
Safety and compliance
The MD underlined the importance of strict safety norms at construction sites, directing mandatory use of protective gear for workers and installation of barricades around project areas.
AMRUT 2.0 STP Project, at a glance
Total STPs: 39
Total Capacity: 972 MLD
Total Cost: Rs 3,849.10 crore
Package–I:
STPs: 16 | Capacity: 493.50 MLD | Cost: Rs 1,878.55 crore
Package–II:
STPs: 22 | Capacity: 471.50 MLD | Cost: Rs 1,906.44 crore
PPP Mode (Patel Cheruvu):
STPs: 1 | Cost: Rs 64.11 crore
STPs are being constructed at Aminpur, Tellapur, ICRISAT, Uskebavi, Bachuguda, Timakka Cheruvu, Gandigudem, Peerzadiguda, Nagaram, Narsingi (ORR), Sangam (Bapughat), Hyder Shah Kote, Fatehnagar, Chitrapuri Colony, HPS campus, Meerpet, Masab Cheruvu, Kapra, Raviryal, Bongulur, among other locations.