After TGRERA intervention, long-stalled Jaya Platinum project in Bowrampet gets occupancy certificate
Spread over 2,731.78 square yards, the project consists of a stilt plus five floors with a total of 60 apartments and was registered with TGRERA
By Sistla Dakshina Murthy Published on 11 Jan 2026 3:26 PM IST
Vasavi Lake CityāWest: TGRERA orders Vasavi Realtors to Pay 10.70% interest to home buyers for failing to hand over flats
The case arose from complaints filed by around 30 buyers, including Anasuya, Sushila Nunna, and Ravikiran Nunna, who booked flats in October 2021...
By Sistla Dakshina Murthy Published on 2 Jan 2026 9:02 AM IST
TGRERA halts unauthorised works at Vasavi MPM Grand in Ameerpet after buyer complaints
Across the complaints, the allottees alleged that the developers undertook construction in clear violation of approved GHMC plans
By Newsmeter Network Published on 15 Dec 2025 8:11 PM IST
Builder cannot unilaterally cancel house sale agreement without buyerās consent, rules TGRERA
In its recent order, TGRERA directed the complainant to redeposit the Rs 50 lakh within 15 days into the developerās account
By Sri Lakshmi Muttevi Published on 2 Dec 2025 9:20 AM IST
Hyderabad: TGRERA orders Surabhi Estates to refund Rs 35 lakh to buyer over project violations
The authority held that the builder collected large sums from the public without securing mandatory clearances and issued cheques that later bounced
By Newsmeter Network Published on 23 Nov 2025 12:13 PM IST
Hyderabad: Aditya Constructions asked to refund ā¹82.43L to man who booked flat in its Aditya Capitol Heights project
The buyer alleged construction delays exceeding six years, absence of an Occupancy Certificate, and failure to stipulate a possession timeline in the...
By Newsmeter Network Published on 22 Nov 2025 10:38 AM IST
TGRERA fines Bhuvanteza Infra Rs 6.4L; directs to refund money to buyers for delayed projects
The authority also directed the builder to refund the entire amount paid by buyers, along with interest ranging from 10.7% to 10.75% per annum
By Sistla Dakshina Murthy Published on 8 Oct 2025 9:19 AM IST
TGRERA fines Jubilee Hills Housing Society Rs 18.51L for launching residential project without approvals
The society floated āJubilee Hills Phase-4ā, a 13.7-acre high-rise venture comprising 1,910 units across 40 floors
By Sistla Dakshina Murthy Published on 9 Sept 2025 11:51 AM IST
Hyderabad: TGRERA asks `The Building Co' to pay Rs 35L to homebuyer over project delay
The directive, issued on September 4, stems from a complaint regarding the 'TBC Rasagna North' project in Kompally
By Sistla Dakshina Murthy Published on 9 Sept 2025 8:43 AM IST
Rangareddy: TGRERA fines Googee Properties Rs 27L for selling plots without approvals at Nomula
Over two years later, the site remained undeveloped, with no demarcation of plots
By Sistla Dakshina Murthy Published on 15 Aug 2025 8:41 AM IST
TGRERA fines Haris Pranava Builders, Whistling Meadows developers for violations, puts names on blacklist
The action comes following multiple complaints from homebuyers regarding construction deficiencies and project non-registration
By Sistla Dakshina Murthy Published on 6 Aug 2025 5:21 PM IST
TGRERA orders Jayathri Infra to return Rs 11.6 lakh for undelivered project in Serilingampally
TGRERA has directed the developer to refund the entire paid amount